DEPARTMENT WISE PROGRESS REPORT OF AREA BASED PROJECT FOR ST UNDER SOUTH TRIPURA DISTRICT DURING THE MONTH OF APRIL 2005.

PUBLIC WORKS DEPARTMENT

 

Name of Project

Details of works to be under taken

Physical target

Proposed amount (In lacs)

Target fixed/ Action to be taken.

Action taken

I

II

III

IV

V

VI

Gagan Chandra Para (Sabroom)

Formation works, Brick soling road, Pucca side drain & C.D. etc.

1. Const. of road from Donamohan para to Maniram bari via Mansing  para, Debdas para & Gagan Ch. Para JB School

 

 

4.50 KM

 

 

40.46

Estimate would be prepared for two items for current year 2004-2005 and sent to EE, P. W. D, Sabroom and copy to SE, PWD, South Tripura, Udaipur. S. D. M, was instructed to prioritize 2 roads with detailed information i.e. availability of land, viability, minimum no. of  cross drainage works.

Estimates for 2-road constn. has been sent for necessary sanction. Namely- i. Annaprasad para to Maniram bari via Monshing para. ii. Maniram para to Kalir bazaar via Commila Rj. Para. This road constn. is very vital for implementing other schemes works inside Special Area Project.

2. Maniram para to Kalirbazar via Budhu Tripura para.

2.50 KM

34.51

3. Shil Tilla to US road via Howaibari para, Pusparam para to Bhumihin Collony.

5.00 KM

43.66

4. Manirambari road to Annaprassad para via Kalijoy para.

4.00 KM

32. 79

5. Hawaibari to Debtabari via Jaba Kr. Tripura para.

4.00 KM

33.11

Total involvement amount:

 

184.53

 

NIL.

Laxmichara (Belonia)

1. Const. of Tairuma Bazar to Raibari road. Earth work in formation and soling.

7.00 KM

75.005

Estimate would be prepared for two items and sent to SE, P.W.D, South Tripura, Udaipur.

 

 

 

 

As per report of SE, Sl. No. 5, 6 & 7 are almost complete. SE was requested to take Sl. No. 1 & 2 in this year. SDM also intimated that for Sl. No. 3 sanction is available as far he is aware.

Estimate will be framed on receipt of decision from the competent authority.

2. Const. of road from Tairuma Bazar to Durgabari via Desharai Para.   Earth work in formation and soling

7.00 KM

63.00

SDM, Belonia has requested to take up the work during current financial year. An estimate amounting to Rs. 48.11 lakhs for 4.5 KM to CE (PWD) Agt.   

3. Const. of road from Desharai Para to Bagafa Ashram School via Chulaibari.    Earth work in formation and soling.

5.00 KM

50.00

Estimate will be framed on receipt of decision from the competent authority.

4. Const. of road from Tairuma to Kalashi Bazar via Debjoy Reang Para. Earth work in formation and soling

8.00 KM

65.00

Estimate will be framed on receipt of decision from the competent authority.  

5. Improvement of road from Baikhora to Birendra Nagar via Laxmichara.  Widening & shouldering at 6.40 KM to 12.20 KM (Location is improvement of road from southem point of Laxmichara village to Griddhi Kr. Para)

6.40 KM

18.280

Work completed. Up to date expenditure Rs. 8.29 lacs for 5.6 KM

6. Const. of RCC Box cell bridge, 3 cell to replace the SPT bridge over local chara on Laxmichara to Raibari road. (Location is const. of RCC box cell bridge at Ramtafa Para on Laxmichara-Raibari road)

1

19.750

Nearing completion. In the meantime the structure opened to traffic. Up to date expenditure is Rs. 13.83 lakhs for 1 no.

7. Grouting and re-carpeting on Baikhora to Birendranagar via Laxmichara road.

3.40 KM

11.810

Grouting and re-carpeting completed. For a length of 6.10 KM. Up to date expenditure is Rs. 10.12 lakhs. The work is in completion stage. 

Total involvement amount:

 

302.845

 

Total expenditure is Rs.  32.24 lakhs

Dakshin & Uttar Songang, (Amarpur)

1.Road formation of link road

12.00 KM

2.40

4 KM brick soling may be takes up during this year. SDM will prioritize the roads where minimum cross drainage works are required and land is also available. The detailed information, i.e. no. of bridges, culverts (with length), length of road etc. for each road will be furnished by SDM to PWD.

 

2. Brick soling roads

10.00 KM

29.00

 

3. Road slab culvert:-

i.                      Dulongbari to Serthum Kalai Para-6

ii.                     Serthum Kalai to Serthum Molsom Para-2

iii.                    Serthum Molsom to Serthum Reang Para-6

iv.                   Serthum Kalai to Manduchara-5

v.                    Kamlaibari to Bongshi Para-5

24 nos.

44.16

 

4. Const. of bridges-

i.                      Sonachari to Satakara para-1

ii.                     Amarpur-ampi PWD road to Kamlaibari-1

iii.                    Tentuibari to Serthum Kalai para-2

iv.                   Amarpur-ampi PWD road to Dulongbari-2

6 nos.

 

 

Total involvement amount:

 

75.56

 

NIL.

South Barmura, (Udaipur)

1. Brick soling road from Nitya bazaar to Bampai Bari-

5.00 KM

95.60

SE PWD was requested to take up at least 2 KM of Katcha link road from Nitya bazaar to Bampai Bari.

Estimate was submitted for obtaining sanction but not yet sanction received.   

2. Resoling of road from Pitra to Nitya Bazer

3.00 KM

27.000

Tender accepted for resoling

 Work in progress 50% work already completed.  

3. Brick soling road from Nityabazar to Kalsibari via Rainya bari, Dumbur bari

   

7.00 KM

126.41

 

 

 Total involvement amount:

 

 249.01

 

NIL.

POWER DEPARTMENT

 

I

II

III

IV

V

VI

Gagan Chandra Para (Sabroom)

For Gagan para: [Extension of LT line]

i.                      Poangbari para- 1.5 KM

ii.                     Adibasi para- 1.0 KM

iii.                    Kumilla para- 1.5 KM

iv.                   Monsing para-1.0 KM

For Gardhang

v.                    Hawaibari para-1.0 KM

vi.                   Pusparam para-2.0 KM

vii.                  Bhubanbasi para-2.0 KM

10.00 KM

28.000

5 KM at Gagan Ch. Para & 5 KM at Gardhang para would be taken up during this year.

 

SDM was instructed to communicate each and every specific item of work, which is required to be taken up.

 

SE (Power) inform that, for new extension, advance booking by consumers at least @ 20 consumers (minimum)/KM is needed to make any project viable. The Project committee will submit an under taking in this regard. 

Estimate for extension of un-electrified paras in Gagan & Gardhang GPs has been sent for necessary sanction.

Total involvement amount:

 

28.00

 

NIL.

Laxmichara (Belonia)

1. Extension of HT line for electrification of village

22 KM

38.060

Power Deptt has forwarded estimate for 22 KM to Govt. of Tripura.

 

SDM, was suggested to prioritize N. Binoy Prasad para, Bancha para & Girdhi Kr. Para during the current year. SDM was instructed to approach in a shape of letter for each specific item of work, which is needed to be taken up.

 

SE (Power) informed that, for new extension advance booking by consumers at least @ 20 consumers (min.)/KM is needed to make it viable. It was decided that the Project committee would ensure this.

Estimate for 22 KMs has been submitted to the Govt. Item wise prioritization of works will be decided in the Project Committee meeting. Panchayat Samiti BGF approved for 6 KM HT line this year. 

2. Extension of HT line for energisation  of PHE pump

1.5 KM

2.595

Estimate submitted. Tentative sanction accorded by the CE (Elec)

3. Extension of HT line for energisation of MI pump

2.5 KM

4.325

Estimate submitted. Tentative sanction accorded by the CE (Elec)

4. Installation of distribution sub-station for electrification of 5 villages-

a)        63 KVA-

b)        25 KVA

 

3

2

 

1.800

0.920

Estimate submitted to the CE (Elec).

5. Installation of distribution sub-station for energisation of PHE pump- 63 KVA

1

0.600

Estimate submitted to the CE (Elec). 

6. Installation of distribution sub-station for exercitation of MI pump- 63 KVA

2

1.200

Estimate sent to MI Deptt. 

7. Extension of LT line for electrification of 5 villages

7.5 KM

11.775

Panchayat Samiti, Bagafa approved target for 1.5 KM at North Banoy Prasad Para. 

8. Internal electrification i/c providing of service connection for BPL families

378

3.507

 

No action taken.

Total involvement amount:

 

64.782

 

NIL.

Dakshin & Uttar Songang, (Amarpur)

Electricity extension of LT/HT line

 

 

 

 

10.00 KM

25.00

 

4 K.M H. T & 1 KM L. T line may be taken up during this year. SDM was instructed to approach in a shape of letter for each specific item of work, which is needed to be taken up. SE (Power) informed that, for new extension advance booking by consumers @ 20 consumers (min.)/ KM is needed to make it viable. The Project committee will ensure this.

Estimate submitted by SDO (Elect) Ompi. i. Marus Bari (South Songang) –2.45 KM for HT & LT line and 1 Sub-Staten . Estimate cost Rs. 4.3305

ii. Bangsi para (South Songang)- 2.95 KM for HT & LT line and 1 Sub-Staten. Estimate cost Rs.  5.14652 lakhs. iii. Kalai para-1.00 KM for HT & LT line and 1 Sub-Staten . Estimate cost Rs. 1.34757 lakhs.

Total involvement amount:

 

25.00

 

NIL.

South Barmura, (Udaipur)

Electricity extension of LT/HT line. Bampuibari and Tuicharbari.

5.00 KM

8.50

First Nityabari is to be connected. SDM will fix up date for holding service connection camp at Nityabari. If it becomes fruitful then extension will be considered for Bampaibari & Tuicharbari.

 

SDM was instructed to approach in a shape of letter for each and every specific item of work, which is required to be taken up. 

Estimate prepared and send to Chief Engineer for sanction.

Total involvement amount:

 

8.50

 

NIL.

AGRICULTURE DEPARTMENT:

 

I

II

III

IV

V

VI

Gagan Chandra Para (Sabroom)

1. Seed replacement for increasing production and productivity of paddy/rice

8 MT

1.30

This year target of 4 MT. Amount earmarked is Rs. 0.65 lakh

Not yet done.

2. (a) Improvement of Jhum Cultivation by Jhumias-

    (b) Training for Jhumias

60 Hec.

150 nos.

2.40

0.15

Not to be taken up in the currant year.

Not yet done.

3. Creation of home stead garden by fruit plants like Mango, Coconut, Areca nut etc.

350 families

7.00

200 families.  Amount earmarked is Rs. 2.00 lakhs.

Not yet done.

4. Horticulture plantation (by Cashew-nut, Orange) by improved grafts.

70 Hec.

14.00

 

 Not yet done.

5. Land Development Work-

10 Hec.

1.50

Not taken up.

 

6. Vegetable cultivation

10 Hec.

1.30

-

 

7. Crop demonstration on paddy

15 Hec

1.00

-

 

Total involvement amount:-

 

 28.65

 

NIL.

Laxmichara (Belonia)

A) AGRICULTURE ACTIVITIES: 1. Crop demonstration by High yielding varieties.

 125 Hec.

2.50

 Agri. Dept.  will implement from their own source.

Expenditure incurred Rs. 0.64 lakh for 32 Hec by Agri. Deptt.  

Total involvement amount

 

2.50

 

Total expenditure incurred Rs. 0.64 lakhs

B) HORTICULTURE ACTIVITIES 1. Summer season vegetables cultivation.

4.5 Hec.

0.675

For this year Rs. 0. 20 lakh approved.

Expenditure incurred Rs. 0.156 lakh for 1.7 Hec by Agri. Deptt.  

2. Winter season vegetables cultivation

12.0 Hec.

 1.80

For this year 12 Hec, Rs. 1.80 lakh approved. Pea, Potato, Tomato & Chilly cultivated.

Expenditure incurred Rs. 0.324 lakh for 2.5 Hec.

3. Horticultural plantations i. Cashew nut plantation

32.5 Hec.

1.95

15 Hec.

Expenditure incurred Rs. 0.90 lakh for 15 Hec.

ii. Pineapple plantation

5.0 Hec.

0.50

From Horti. Dept. source.

Expenditure incurred Rs. 0.39 lakh for 3 Hec. Work order issued for another 5 Hec. of land. Work started.

iii. Banana plantation

30.0 Hec.

3.00

From Horti. Dept. source.

Expenditure incurred Rs. 0.65 lakh for 5 Hec. Work order issued for another 5 Hec. of land. Work started.

iv. Jack fruit plantation

5.0 Hec

0.175

From Horti. Dept. source.

Not yet take up.

v. Papaya plantation

5.0 Hec.

0.650

From Horti. Dept. source

Expenditure incurred Rs. 0.065 lakh for 0.5 Hec.

vi. Orange cultivation

2.0 Hec

0.10

From Horti. Dept. source

Expenditure incurred Rs. 0.12lakh for 25 Hec. Completed.

vii. Amarapalli cultivation

1.00 Hec.

0.075

From Horti. Dept. source

Expenditure incurred Rs. 0.075 lakh for 1 Hec . Completed.

4. Percolation tank/ Farm ponds

24 nos.

2.40

For this year 2 nos. & Rs. 2.40 lakhs approved.

Expenditure incurred Rs. 0.70 lakh for 7.

5. Rehabilitation components

42 units

0.840

Few essential Agri. equipments like Spade, Scissor etc. to be provided @ Rs.10/- would be taken as beneficiary contribution and rest from Project fund. Same action should be taken by other SDMs also.

Expenditure incurred Rs. 1.12 lakh for 41 units.  

6. Water harvestinh structure (WST)

7 nos.

1.05

 

Expenditure incurred Rs. 0.79lakh for 5 nos.

Total involvement amount:

 

13.225

 

Total expenditure incurred Rs.  5.29 lakhs

Grant total (A+B):

 

15.375

 

Total expenditure incurred Rs.  5.93 lakhs

Dakshin  & Uttar Songang, (Amarpur)

1. Target for Garden pea mini kit demo.  

 34 families

 

 

 

                                                                      Total involvement amount:

 

NIL.

 

NIL.

South Barmura, (Udaipur)

Horti Plantation (Technology Mission) :- 1. Banana-

15.00 Hec.

1.95

 

Expenditure incurred Rs. 1.95 lakh for 15 Hec.

2. Litchi-

2.20 Hec.

0.236

 

Expenditure incurred Rs. 0.236 lakh for 2.2 Hec.

3. Assam lemon

2.00 Hec

0.260  

 

Expenditure incurred Rs. 0.26 lakh for 2 Hec

4. Black papper

0.50Hec

0.120

 

Expenditure incurred Rs. 0.12 lakh for 0.5 Hec

5. Orange plantation-

4.00 Hec

0.520      

 

Expenditure incurred Rs. 0.52 lakh for 4.00 Hec

6. Pine apple

3.00 Hec.

0.39

 

Expenditure incurred Rs. 0.39lakh for 3.00 Hec

7. Winter Vegetable

6.00 Hec.

0.76436

 

Expenditure incurred Rs. 0.76436 lakh for 6.00 Hec

8. Summer vegetable

2.20 Hec.

0.286

 

Expenditure incurred Rs. 0.286 lakh for 2.2 Hec

9. State plan:- Integrated scheme for improved production & Productivity of Jhum.

4.00 Hec.

0.54

 

Expenditure incurred Rs. 0.54 lakh for 4.00 Hec

10. PDF Scheme- i. Aman Paddy Minikit

                             iii. Winter Vegetable (Rabi)

2.50 Hec

9.75 Hec

0.035

0.13578

 

Expenditure incurred Rs. 0.035 lakh for 2.50 Hec

Expenditure incurred Rs. 0.13578 lakh for 9.75 Hec

11. Food revival programme- Distribution of Urea Minikit @ 38 Kg. per unit

10 units

0.0195

 

Expenditure incurred Rs. 0. 0195 lakh for 10 units.

Total involvement amount:

 

5.25664

 

Total expenditure incurred Rs. 5.25664 lakhs

 

EDUCATION DEPARTMENT :

 

I

II

III

IV

V

VI

Gagan Chandra Para (Sabroom)

Supply of furniture to (Joint bench for Students, Teachers Table & Chair)

i.                      Gagan Ch. Para JB School

ii.                     Gardang-Poangbari JB School

iii.                    Rangadhan Roaja para JB School

iv.                   Annaprasad para JB School

 

4 School

 

1.50

 

All SDMs will submit requirement of furniture. Dy. Dir. Education will arrange from fund under SSA.

 

Supply has been completed for 3 schools. Remaining 1 school will be supplied.  Expenditure incurred Rs. 1.21769 lakh.

Total involvement amount

 

1.50

 

Total expenditure incurred Rs. 1.21769 lakhs

Laxmichara (Belonia)

1. Setting up of new Pry. School under SSA scheme at Uttar Benoy prasad para (un served). i. Const. of pucca building

 

1

 

5.00

 

To be taken under SSA.

 

Proposal initiated to the Edu. Deptt. Approval not yet accorded.

ii. Provision of furniture

-

0.30

All SDMs will submit requirement of furniture. Dy. Dir. Education will arrange from fund under SSA.

Proposal initiated to the Edu. Deptt. Approval not yet accorded.

iii. Wages of Teachers

2

0.52

-

Proposal initiated to the Edu. Deptt. Approval not yet accorded.

iv. Misc. management expenditure.

-

0.18

-

Proposal initiated to the Edu. Deptt. Approval not yet accorded.

2. Setting up of new upper primary at Desharai  para JB School (SSA)

i. Provision of furniture

 

 

 

0.25

 

All SDMs will submit requirement of furniture. Dy. Dir. Education will arrange from fund under SSA.

 

 

Supply order will be issued by the I/S, TTAADC, Manu. Fund is available.

ii. Wages of Teachers

3

1.00

-

Not required at this stage.

iii. Misc. management Exp.

 

0.25

-

Not required at this stage.

3. Setting up of EGS & AIE Centers- i. Management Exp. of EGS (Pry)

1

0.31

-

EGS centre already opened and running. Fund is available with the I/S Santirbazer.

ii. Management Exp. of AIE

1

0.31

-

AIE centre not started.

4. Up- gradation of Benoy Prasad Para SB School.

1

1.25

Dy. Dir., Education will take up.

Proposal submitted to the Education Deptt.

5. Const. of pucca building at TW Colony JB School.

1

5.00

Dy. Dir., Education will take up

Expenditure incurred Rs. 2.497 lakh for 1 no. Work order issued by the BDO, Bagafa with fund under SSA of Edu. Deptt . Work completed.

Total involvement amount:

 

14.37

 

Total expenditure incurred Rs. 2.497 lakhs

Dakshin  & Uttar Songang, (Amarpur)

1.  Construction of school building.

1

8.25

Dy. Dir.  Education will take up

 

2.  School furniture.

5 schools.

2.50

All SDMs will submit requirement of furniture. Dy. Dir. Education will arrange from fund under SSA.

Not report submitted.

Total involvement amount:

 

10.75

 

NIL.

South Barmura, (Udaipur)

1.Construction of school building at Kalshibari

 1

5.00

During this financial year 2004-05, one School building will be taken up under SSA.

Proposal sent to District Edu office for placement of fund amount Rs. 5 lakhs. Work will be started in 2nd phase but model to be changed.

2. Supply of furniture in schools

6

1.26868

Inspector of school TTADC is requested to sent a list of additional requirement school wise to SDM, UDP.

Expenditure incurred Rs. 1.26868 lakh for 6 JB Schools. Supply of furniture to the schools at Dakbari, Rainyabari, Kalshibari, Thalibari, Bampai bari, Sukmohan bari Schools. Supply completed.

Total involvement amount:

 

6.26868

 

Total expenditure incurred Rs.   1.26868 lakhs.

 

ANIMAL RESOURCES DEVELOPMENT DEPARTMENT:

 

I

III

III

IV

V

VI

Gagan Chandra Para (Sabroom)

1. Piggery scheme (2:1) @ Rs. 12,000

55 families

6.60

For this year 20 families and an amount of Rs. 2.40 lakhs approved. ARD Dept. will implement these activities.

Not report submitted.

2. Goatery scheme (2:1) @ Rs. 3,000

60 families

1.80

For this year 60 families (4:1) and an amount of Rs. 3.00 lakhs approved. ARD Dept. will implement these activities.

Not report submitted.

3. Poultry scheme (50) @ Rs. 5,000

35 families

1.75

Approved.

Not report submitted.

4. Duckery scheme (50) @ Rs. 5,000

25 families

1.25

No to be taken up at present.

 

Total involvement amount:

 

11.40

 

NIL.

I

III

III

IV

V

VI

Laxmichara (Belonia)

1. Poultry local scheme

100 unit

3.00

No to be taken up at present.

 

2. Milch cow (ND)

75 unit

6.00

No to be taken up at present.

 

3. Stockman sub-centre

1 no.

2.45

No to be taken up at present.

 

4. Fodder cultivation (silvi pasture) & Tapioca cultivation

24 acres

0.72

No to be taken up at present.

Tapioca will be cultivated in 10 acres.

Total involvement amount

 

12.17

 

NIL.

Dakshin & Uttar Songang, (Amarpur)

1. Const. of Veterinary dispensary

1

2.56

No action at present. 

 

3. Goatery

20 families

1.00

For this year 20 families and an amount of Rs. 1.00 lakh approved.  ARD Dept. will implement these activities.  

Not report submitted.

Total involvement amount:

 

3.56 

 

NIL.

South Barmura, (Udaipur)

1. Open of a Vety. Sub-Centre

1

Nil

 

 Proposal initiated for Govt. approval. 

Total involvement amount:

 

Nil

 

NIL.

 

I & FM DEPARTMENT:

 

I

II

III

IV

V

VI

Laxmichara (Belonia)

1. Drilling of irrigation deep tube well at  Bhaktirampara.

1

7.00

 

Proposal submitted to the Water Resource Deptt.

2. Const. of semi permanent pump house i/c installation of pump motor

1

3.00

 

Proposal submitted.

3. Extension of GI & UPVC line (i/c with cost of pipes)

2000 Mts

4.00

 

Proposal submitted.

Total involvement amount

 

14.00

 

NIL.

Dakshin  & Uttar Songang, (Amarpur)

1. Minor Irrigation

4 nos.

56.00

 

Expenditure incurred Rs. 8.50 lakhs for 1 no. Work order issued.

Total involvement amount:

 

56.00

 

Total expenditure incurred Rs.   8.50 lakhs.

South Barmura, (Udaipur)

1. LI Scheme at Nityabazer- i. Near Debtamura 

ii. Near old VLW store

2

18.00

 

i. Near Debtamura HS- Estimate submitted for ST

ii. Near old VLW store- Expenditure incurred Rs. 9.00 lakhs for 2 no Require electric connection. Fund placed to Power deptt.

2. Diversion scheme at Bampaibari

1 no.

-

Joint visit with April. Department completed. Proposal sent the EE, IFM for approval.

Proposal sent to EE ,I & FM for approval.

Total involvement amount:

 

18.00

 

Total expenditure incurred Rs.   9.00 lakhs.

 

FISHERIES DEPARTMENT

 

I

II

III

IV

V

VI

Gagan Chandra Para (Sabroom)

1. Drag net

 

Nil

For this year 2 nos. SHG. and an amount of Rs. 0.40 approved. Fishery Deptt. will implement these activities.

Not reported submitted.

Total involvement amount:

 

NIL.

 

NIL.

Laxmichara (Belonia)

1. Training of fish farmers (3 days)

150 nos.

0.225

--

Will be organized this year.

2. Drag net

2 nos.

0.40

For this year 2 nos. SHG and an amount of Rs. 0.40 approved. Fishery Deptt. will implement these activities.

 Not reported. 

3. Social fishery

10 nos.

0.05

 

Expenditure incurred Rs. 0.05 lakhs for 10 nos Work completed.

Total involvement amount:

 

0.675

 

Total expenditure incurred Rs.   0.05 lakhs.

Dakshin  & Uttar Songang, (Amarpur)

1. Integrated Fish culture

 

 

For this year 20 families and an amount of Rs. 3.0 lakhs approved. Fishery Deptt. will implement these activities.

Not reported submitted. 

2. Supply of cast net

 

 

For this year 15 families and an amount of Rs. 0.18 lakh approved. Fishery Deptt. will implement these activities.

Not reported submitted.

Total involvement amount:

 

Nil

 

NIL.

South Barmura, (Udaipur)

1. Drag net

 

 

For this year 2 nos. SHG and an amount of Rs. 0.40 approved. Fishery Deptt. will implement these activities.

 

2. Integrated aquaculture with pig

2

0.30

 

Expenditure incurred Rs. 0.30 lakhs for 2 nos. Work completed

3. Supply of MC fish seed @ 1000 nos. each

25

0.075

 

Expenditure incurred Rs. 0.075 lakhs for 25 nos. Work completed

4. Supply of Medicine

14 families

Nil

 

Work completed

Total involvement amount

 

0.375

 

Total expenditure incurred Rs. 0.375 lakhs.

 

SOCIAL EDUCATIONAL DEPARTMENT

 

I

II

III

IV

V

IV

South Barmura, (Udaipur)

Construction of ICDS centres- i. Sukmohan bari, ii. Puskirini bari, iii. Tuicharbari, iv.Temtai bari, v. Naklibari.

5

 

 

  Approval not yet received.

Total involvement amount:

 

NIL.

 

NIL.

 

FOREST DEPARTMENT :

 

I

II

III

IV

V

IV

South Barmura, (Udaipur)

Joint forest management at Nityabari, Dumburbari, New life JFM (Rainya bari)

218 hec. Teak/ Gamair/Kathal plantation. Water reservoir (0.8 Hec.)

3.64825

 

 Expenditure incurred Rs. 1.63177 lakhs for 45.8 Hec.

Total involvement amount:

 

3.64825

 

Total expenditure incurred Rs.   1.63177 lakhs.

 

RD DEPARTMENT

 

II

II

IV

V

VI

 

Gagan Chandra Para (Sabroom)

1. Housing (IAY) Mud wall

31

 

 

17 houses. Work to be taken up BDO, STC Block.

2. Up-gradation of house

17

 

 

17 houses. Work to be taken up BDO, STC Block.

3. C K T house

 

 

 

16 CKT house. Work to be taken up BDO, STC Block.

4. Repairing of pond reservoir.

 

 

 

Selection of beneficiaries has been submitted to the fishery Deptt. Work will be taken up shortly.

5. Const. of Angawadi Centre building- i. Gagan Ch. Para-2, ii. Gardang area-2

4

10.00

SDM, Sabroom will take up the matter with concerned BDO for construction of 2 (two) new centers.

Work has been taken up BDO, STC, Block. (SDM Sabroom will clarify)

6. Distribution of HC spray out subsidy

200 nos.

3.00

This year 200 nos.(Full)  action may be taken by BDO, Satchand.

 

7. Distribution of Pump set for irrigation.

25 nos.

5.00

To be covered under RD schemes.  

 

8. Repairing of Tank/Mini Reservoir at Gagan Ch. para

12 unit, 1.44 Hac

 0.96

Concerned BDO will take up from SGRY fund.

Work is being taken up by BDO, STC. List of selected beneficiaries has been submitted to the Fishery Deptt. & works will be taken up shortly.

9. Repairing of Tank/Mini reservoir at Gardhang area

 10 unit, 1.6 Hac

 0.80

Concerned BDO, Satchand Block will taken up from SGRY fund

Work is being taken up by BDO, STC. Selection of beneficiaries has been submitted to the Fishery Deptt. & works will be taken up shortly.

10. Const of market stalls

3 rooms

1.23

 

Expenditure incurred Rs. 1.23 lakhs for 3 rooms market stalls. Work completed.

Total involvement amount:

 

 20.99

 

Total expenditure incurred Rs.  1.23 lakhs.

Dakshin & Uttar Songang, (Amarpur)

1. Housing (IAY) Mud wall

46

 

 

Expenditure incurred Rs. 11.655 lakhs for 37 families, 25% completed.

2. Housing (IAY) Non-mud wall

 

 

Expenditure incurred Rs. 2.475 lakhs for 9 families, 25% completed

3. Up-gradation of house

27

 

 

Expenditure incurred Rs. 2.70 lakhs For 27 families, 25% completed

Total involvement amount:

 

NIL.

 

Total expenditure incurred Rs. 16.83 lakhs.

II

II

IV

V

VI

 

South Barmura, (Udaipur)

1. i. Housing (IAY), 

49

15.675

 

Expenditure incurred Rs. 15.675 lakhs for 57 houses completed.

   ii. Housing (PMGY)

8

2. Up-gradation house.

32

4.00

 

Expenditure incurred Rs. 4.00 lakhs for 32 houses completed.

3. Drinking water source-

i.                      Traditional source,

ii.                     Masonry well

iii.                    Sanitary well

 

iv.                   Mark-III 

 

1

1

4

 

1

 

0.15

2.15884

1.3916

 

0.3514

 

 

 

 

i. Work in progress of Bampaibari

ii. Deeg 15 ft. at Bampaibari.

iii. Work in progress at Bampabari, Sukmohanbari, Rainyabari & Kalshibari JB School

iv.  Work in progress at Dakbari JB School.

4.  Construction of water reservoir

1nos.